To seek approval to undertake a procurement
exercise for drainage works and kitchen refurbishment at Langton
Primary School.
Decision type: Key
Reason Key: Affect on communities;
Decision status: Recommendations Approved
Notice of proposed decision first published: 15/12/2023
Decision due: 19 Feb 2024 by Assistant Director - Property, Procurement & Commercial
Lead member: Deputy Leader & Executive Member for Finance & Resources
Lead director: Corporate Director of Resources
Contact: Paula McLean, Corporate Programme Manager, Property Email: paula.mclean@northyorks.gov.uk Email: paula.mclean@northyorks.gov.uk.
Consultation process
No further consultation is required. The
decision to procure follows on from the previous decisions to fund
capital works at Langton Primary School.
Consultees
The scheme is being funded from the CYPS
School Condition Grant approved by The Executive. Further
consultation has been undertaken with the School and CYPS
Officers.