Issue details

Scarborough West Pier Bullnose and Lighthouse Pier Pile Replacements

To approve a budget to enable the commencement of a procurement for i) employment of a contractor to design and build the works and ii) employment of a consultant to project manage and supervise the works, and the subsequent entering into contracts to perform the works and the services.

Decision type: Key

Reason Key: Expenditure/savings > £500,000 & Affects more than one division;

Decision status: Not to be progressed

Notice of proposed decision first published: 25/11/2025

Decision due: 20 Jan 2026 by Executive

Lead member: Executive Member for Open to Business

Lead director: Corporate Director of Environment

Contact: Chris Bourne, Head of Harbours and Coastal Infrastructure Email: chris.bourne@northyorks.gov.uk Email: Chris.Bourne@northyorks.gov.uk Email: chris.bourne@northyorks.gov.uk.

Consultation process

Via Harbour User Group; statutory consultations ie planning, MMO Licences, etc

Consultees

Local ward members
Scarborough Town Council
Scarborough Harbour users