To consider increasing contingency budget for the Selby Transforming Cities Fund (TCF) project from draw-down of the Council’s capital contingency reserve following notification of cost increases/contract compensation events related to scheme delivery.
Decision type: Key
Reason Key: Expenditure/savings > £500,000;
Decision status: Not to be progressed
Notice of proposed decision first published: 13/03/2026
Decision due: 21 Apr 2026 by Executive
Lead member: Executive Member for Highways & Transportation
Lead director: Corporate Director of Environment
Contact: Alex Richards, TCF Programme Delivery Manager Email: alex.richards1@northyorks.gov.uk Email: Alex.Richards1@northyorks.gov.uk Email: alex.richards1@northyorks.gov.uk.
Consultation process
Briefings
Consultees
Corporate Director - Environment and Executive Member for Highways and Transportation