Decision to undertake a procurement exercise
for proposed upgrading works to the existing streetscape on land at
Low Street East in Sherburn In Elmet.
The procurement exercise is programmed to commence in 12.08.24
utilising the YORbuild framework. The scheme is programmed to start
on site in December 2024 and is due to complete in June 2025. The
total value of scheme £800k. There is external funding from
the UK Shared Prosperity Fund of £300k which must be spent by
end of March 2025.
Design work undertaken by Align PP.
Planning Permission granted on 01.05.24 (Decision No
ZG2023/1268/FUL).
Decision type: Key
Reason Key: Expenditure > £500,000;
Decision status: Recommendations Approved
Notice of proposed decision first published: 17/05/2024
Decision due: 17 Jun 2024 by Corporate Director of Community Development
Lead member: Executive Member for Open to Business
Lead director: Corporate Director of Community Development
Contact: Rachael May Email: melissa.pollard@northyorks.gov.uk Email: rachael.may@northyorks.gov.uk.
Consultation process
INTERNAL:
Teams meetings
Emails
In person briefings
EXTERNAL:
Showcase event open to members of public organised by Sherburn Town
Council on 20.01.24.
Landowner consultation event which happened on 3rd October 2023 we
presented the plan to all landowners and business tenants and Town
Councillors.
Consultees
Corporate Director of Community
Development.
Assistant Director of Economic Development, Regeneration, Tourism
and Skills.
Head of Regeneration.
Procurement.
Finance.
Legal.
Executive Member for Open to Business.)
Business tenants.
Landowners.
Local community.