Issue details

Low Street public realm improvements, Sherburn in Elmet

Decision to undertake a procurement exercise for proposed upgrading works to the existing streetscape on land at Low Street East in Sherburn In Elmet.

The procurement exercise is programmed to commence in 12.08.24 utilising the YORbuild framework. The scheme is programmed to start on site in December 2024 and is due to complete in June 2025. The total value of scheme £800k. There is external funding from the UK Shared Prosperity Fund of £300k which must be spent by end of March 2025.

Design work undertaken by Align PP.
Planning Permission granted on 01.05.24 (Decision No ZG2023/1268/FUL).

Decision type: Key

Reason Key: Expenditure > £500,000;

Decision status: Recommendations Approved

Notice of proposed decision first published: 17/05/2024

Decision due: 17 Jun 2024 by Corporate Director of Community Development

Lead member: Executive Member for Open to Business

Lead director: Corporate Director of Community Development

Contact: Rachael May Email: melissa.pollard@northyorks.gov.uk Email: rachael.may@northyorks.gov.uk.

Consultation process

INTERNAL:
Teams meetings
Emails
In person briefings

EXTERNAL:
Showcase event open to members of public organised by Sherburn Town Council on 20.01.24.
Landowner consultation event which happened on 3rd October 2023 we presented the plan to all landowners and business tenants and Town Councillors.

Consultees

Corporate Director of Community Development.
Assistant Director of Economic Development, Regeneration, Tourism and Skills.
Head of Regeneration.
Procurement.
Finance.
Legal.
Executive Member for Open to Business.)
Business tenants.
Landowners.
Local community.